In the period 23 -26 May, 2022, the company “Institute IGH” a.d. (JSC) Zagreb performed the test load of the bridge structure, which was constructed as a steel box girder bridge over three spans l=128+170+128=426 m with support on two abutments. The middle of the main...
Investor: Mješoviti Holding „Elektroprivreda Republike Srpske“ ZP „Hidroelektrane na Trebišnjici“ a.d. Trebinje/ MH “Power Utility of the Republika Srpska”, Subsidiary Company “HPPs on the Trebišnjica“ a.d. (JSC) TrebinjeContractor: The Consortium...
Employer: Public company “Autoputevi Republike Srpske“ d.o.o. (LLC) Banja LukaContractor: Integral inženjering a.d. (JSC) LaktašiValue of works: 12.2 million BAM or 6.2 million EURFunding: Local funds The Mayor of Gradiška, Zoran Adžić, and the Assistant Minister in...
After the beginning of works on the construction of the motorway on the bypass near Doboj (Corridor 5c) was officially marked on November 26, 2021, the company “Integral inženjering“ successfully and in accordance with the work schedule performs the works on...
On February 15, 2022 Integral inženjering began works on the construction of the section of the highway Okučani – B&H border / 2nd phase of the total length L = 4.07 km. The beginning of the expressway is just before the “Novi Varoš” junction, while at...
Commissioning of works on the section of motorway on Corridor 5C through the Republika Srpska in the total length of l = 5.6 km was held on November 26, 2021 with appropriate ceremony. This is the second section that Integral inženjering is currently building on...